An anchored lift is only as good as the concrete under it. Every maker publishes its own minimums, so the exact model sets the numbers.

Planning the bay / Checked

Why the slab matters

The anchors hold the columns to the floor. They need enough concrete depth and strength to hold under load.

The ANSI/ALI ALIS standard says surface-mounted lifts go only on concrete floors, that the floor where the lift goes gets a thorough examination, and that a lift is not installed on a floor that is too thin or too weak. The lift maker's instructions are the final word for each model.

BendPak's published minimums, as an example

These figures are from BendPak's published concrete floor requirements for existing floors. Other makers publish their own, and the numbers differ.

Notice the step with capacity. Moving from a 10,000 lb to a 12,000 lb BendPak two-post moves the minimum from 4-1/4 to 6-1/2 inches.

  • Two-posts GP-7, XPR-9 and XPR-10: 4-1/4 inches, 3000 PSI, 28-day aging
  • Two-post XPR-12: 6-1/2 inches, 3000 PSI, 28-day aging
  • Two-posts XPR-15 and XPR-18: 8 inches, 3000 PSI, 28-day aging
  • Most four-posts: 4-1/4 inches, 3000 PSI, 28-day aging
  • Four-posts HD-973P, HDS-35 and HDS-40: 6-1/2 inches

New concrete

Fresh concrete has not reached its strength. BendPak's published minimum cure time is 28 days before a lift is anchored.

For a new slab poured for a lift, BendPak lists 4,000 PSI concrete and a 12 inch minimum thickness. ALIS notes that an install can stretch over several weeks when concrete has to cure, so plan the schedule around it.

Joints, cracks and patches

BendPak's spec says all 3/4 inch anchors must be at least 6 inches away from any expansion seam, control joint or other flaw in the concrete. It also says never to install on hand-mixed concrete, on cracked or defective concrete, or on anything other than concrete.

An old anchor hole, an asphalt patch or epoxy over unknown concrete is not solid concrete either. BendPak supplies its lifts with concrete fasteners that meet the ANSI/ALI ALCTV criteria, so the anchors are part of the lift's design.

Post-tension slabs and in-floor heat

BendPak's manual warns that cutting through a tensioned cable can cause injury or death. It says to confirm the floor is not a post-tension slab, and to contact the building architect or the local building department before drilling if it might be. It notes ground-penetrating radar can help locate the steel.

In-floor radiant heat is the same story. Nothing gets drilled until the slab is scanned. Don't drill to find out.

When the slab won't work

A thin or poor slab doesn't always end the plan. There are usually other answers, and we check the slab before anything is ordered, sometimes with a small test hole.

  • A freestanding four-post. Some four-posts still need anchoring, so we confirm it per model.
  • A scissor lift, with a check of that model's slab spec
  • Mobile columns. ALIS says the floor still needs checking for slope, curbs, holes, cracks, under-floor vaults and thin spots.
  • A new engineered pad poured for the lift

Common questions

How thick does concrete need to be for a two-post lift?

It depends on the model. BendPak's published minimum is 4-1/4 inches for its 7,000 to 10,000 lb two-posts, 6-1/2 inches for its 12,000 lb XPR-12, and 8 inches for its 15,000 and 18,000 lb models, all at 3000 PSI. Other makers publish their own numbers, and we check the spec for your exact lift.

How long after pouring can a lift go in?

BendPak's published minimum is 28 days of cure time. Other makers set their own requirement. For a new slab poured for a lift, BendPak also lists 4,000 PSI concrete and a 12 inch minimum thickness.

Can a lift anchor go near a control joint?

Not close to one. BendPak's spec says all 3/4 inch anchors must be at least 6 inches away from any expansion seam, control joint or other flaw in the concrete. A lift never goes on a crack or a seam.

What if I don't know how thick my slab is?

Write down what you do know, like when it was poured and whether it has in-floor heat or post-tension cables, and don't drill to find out. We check the slab before anything is ordered, sometimes with a small test hole.